Water Line Project 75 East

9/7/22 Project Update:

Crews will be laying asphalt on 75 East Saturday, September 10th. Please plan ahead as driveway access will be blocked for a period of 30-40 minutes while equipment is in front of your home and until the asphalt cools.

8/24/22 Project Update:

The road reconstruction of this project will begin Monday, 8/29 with milling the road and hauling away the debris. Crews will then be grading mid-week, and paving after Labor Day. 

7/9/22 Project Update:

Crews are doing the last tie-in on Monday, 7/11/22, on 475 North. Affected residents have received door hangers. On Tuesday, a new fire hydrant will be installed (no shut-offs required). Project should then be complete.

Thank you for your patience.


6/2/22 Project Update:

As of today 6/2/22, crews have placed 300 feet of new pipe along 75 East with the goal to have the main line installed by 6/9. The following week, crews plan to begin connecting residents to new 8" line. 

There is still one more tie-in to be done at 475 N., with hopeful project completion by 7/1.

Project Update 9.7.22 Paving 75 East

PROJECT OVERVIEW:

The City's water crews will be replacing the aged 6” waterline connected to homes in this area with a new 8” line. As part of this replacement, the City will be bringing the water infrastructure up to current codes and drinking water regulations.

Construction is expected to begin mid-May, 2022 and we estimate work will take 4 to 8 weeks depending on weather and other variables. There will be times during construction when traffic and driveways will be closed and water service will be interrupted. We will inform residents of any planned interruptions; however, due to the nature of this type of work, unplanned water outages and road blockages may occur.

Water Line 75 East 1-page Project Postcard