Week of April 4

This week's Eaglewood Loop Construction Update: MONDAY & TUESDAY, crews will be completing the secondary water line work and all remaining laterals. This requires continued closure of Eaglewood Loop.

WEDNESDAY through FRIDAY, crews will be working between Woodbriar & Rockwood and removing the existing vault near Sego Lily Circle. This will require a detour, although Eaglewood Loop will be open. See map below.

THURSDAY & FRIDAY, crews may begin the road reconstruction process including milling the asphalt.  

Additional work that may be anticipated: removing and replacing sections of curb & gutter, as well as work on waterways at cul-de-sacs. 