Work for week of July 26: Install 12" water line on Eaglewood Loop between Tanglewood Loop and Rockwood Drive

Upcoming Weeks:

Week of August 2: Install service laterals on Eaglewood Loop from Elk Hollow Road moving south past Rosewood

Week of August 9: Complete service laterals on Eaglewood Loop as far south as Rockwood Drive

Traffic Control Plan 2 week of 7-26-21

Residents -- Please note the area of construction and travel accordingly to minimize driving through the active construction area. This help you avoid delays and will allow us to work more efficiently and safely.

Thank you!